Construction update.

Aug 2017

Construction update.

Construction has progressed quickly since we cleared the site a few weeks ago.

Pass by and you will see a clearly identifiable ‘Construction Works Loading Zone’ on Cambridge Street, allowing our team’s quick and efficient access to the site. A far more important outcome however, is that the clearly identifiable zone creates a safe environment for construction crews and neighbourhood traffic.

With demolition now complete, we have been readying the site for extensive earthworks that will include excavation, development of retaining walls, setting foundations and rough in of services. At present, we are over half way with installation of the pilings. This involves drilling or boring the piles deep into the earth then pouring concrete in so that we can secure the area for basement excavation to commence shortly.